Change Order Example for Painters: Price Extra Work Before You Start
A customer asks you to paint a second room after you have already agreed on the first. Before starting, write down the extra work, price it, explain any schedule change and get the customer's agreement. A clear change order helps both sides understand what changed. Example: one extra bedroom The original quote covers one room for $800. The customer asks to add another bedroom. Your estimate for the extra work is 5 labor hours at $40 per hour ($200), plus $120 in paint and materials: $320 in estimated direct costs. You quote $500 for the additional room. Estimated gross profit on the change is $180 ($500 minus $320). Estimated gross margin is 36% ($180 divided by $500). This is not take-home pay: overhead, taxes and other costs may still apply. The revised quoted total is $1,300 before any applicable tax, assuming no other changes. Copyable change-order template Original job and quote: [job reference and amount] Added work: [room, surfaces, preparation, coats and materials] Exclud...